Color, shape, and finish are a matter of taste, but for the pavement to last long, the paving stone surface must be chosen according to the site’s operational requirements:
Paving stones should be ordered with a reserve – 3-8% of the total paving volume.
Any paved area requires curbs – they not only serve decorative functions but also hold the paving in place to prevent it from slipping.
The paving should be jointed to prevent weeds and young saplings from settling in the gaps.
Paving must not be laid sooner than 5 days after production, loaded sooner than 7 days, and heavy machinery weighing more than 2 tons should not be allowed to drive on the paving sooner than 28 days.
Paving production information is located on the pallets.